[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135734,797,1,"单选题","大型储罐的管道与泵或其他有独立基础的设备连接,应在储罐（）合格后安装。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","充水试验",true,{"key":16,"text":17,"correct":18},"B","基础验收",false,{"key":20,"text":21,"correct":18},"C","焊接检验",{"key":23,"text":24,"correct":18},"D","外形尺寸检查","2020版教材P95 \u002F 2019版教材P84 大型储罐的管道与泵或其他有独立基础的设备连接，应在储罐液压（充水）试验合格后安装，或在储罐液压（充水）试验及基础初阶段沉降后，再进行储罐接口处法兰的连接。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]