[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135732,797,1,"单选题","埋地长输管线下沟后，应进行的管道施工工序不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通球试压测径",false,{"key":16,"text":17,"correct":14},"B","管线吹扫、干燥",{"key":19,"text":20,"correct":14},"C","连头（碰死口）",{"key":22,"text":23,"correct":24},"D","防腐蚀",true,"2020版教材P99 \u002F 2019版教材P89 按照一般地段施工的方法，其主要施工程序是：线路交桩→测量放线→施工作业带清理及施工便道修筑→管道运输→管沟开挖→布管→清理管口→组装焊接→焊接质量检查与返修→补口捡漏补伤→吊管下沟→管沟回填→三桩埋设→阴极保护→通球试压测径→管线吹扫、干燥→连头（碰死口）→地貌恢复→水工保护→竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]