[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135720,797,1,"单选题","在架空线路施工的一般程序中，线路测量的下一步骤是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基础施工",true,{"key":16,"text":17,"correct":18},"B","杆塔组立",false,{"key":20,"text":21,"correct":18},"C","放线架线",{"key":23,"text":24,"correct":18},"D","导线连接","2020版教材P84 \u002F 2019版教材P73 架空线路施工的一般程序：线路测量一基础施工一杆塔组立一放线架线一导线连接一线路试验一竣工验收检查。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]