[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135688":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135688,797,1,"单选题","机械设备安装时，设备固定与灌浆的紧前工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","垫铁设置",false,{"key":16,"text":17,"correct":14},"B","设备装配",{"key":19,"text":20,"correct":21},"C","安装精度调整与检测",true,{"key":23,"text":24,"correct":14},"D","吊装就位","2020版教材P70 安装精度调整与检测→设备固定与灌浆",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]