[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135666,797,1,"单选题","精密、大型设备安装基础需要考虑减少基础振幅、减弱基础振动或控制基础沉降等，最适合采用的基础是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扩展基础",false,{"key":16,"text":17,"correct":18},"B","桩基础",true,{"key":20,"text":21,"correct":14},"C","联合基础",{"key":23,"text":24,"correct":14},"D","沉井基础","2020版教材P69 \u002F 2019版教材P58 （1）桩基础。由承台、桩组成的基础形式，可分为预制桩和灌注桩两大类，适用于需要减少基础振幅、减弱基础振动或控制基础沉降和沉降速率的精密、大型设备的基础。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]