[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135664,797,1,"单选题","下列设备基础需要做预压强度试验的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","电机",false,{"key":16,"text":17,"correct":14},"B","压缩机",{"key":19,"text":20,"correct":14},"C","泵",{"key":22,"text":23,"correct":24},"D","汽轮发动机组",true,"2020版教材P69 \u002F 2019版教材P59 （2）重要的设备基础应做预压强度试验,预压合格并有预压沉降详细记录。如大型锻压设备、汽轮发电机组、大型油罐。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]