[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135662,797,1,"单选题","设备安装时，所有设备安装的平面位置和标高，均应以（）为基准进行测量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","车间的实际位置和标高",false,{"key":16,"text":17,"correct":14},"B","设备的实际几何尺寸",{"key":19,"text":20,"correct":21},"C","全厂确定的基准线和基准点",true,{"key":23,"text":24,"correct":14},"D","土建交付安装的中心线和标高","2020版教材P70 \u002F 2019版教材P60 2.基础测量放线 （2）机械设备就位前，应按工艺布置图并依据相关建筑物轴线、边缘线、标高线，划定设备安装的基准线和基准点。基准线和基准点通常由专门的测量人员用测量仪器按测量规程设定，所有设备安装的平面位置和标高，应以确定的基准线和基准点为基准进行测量。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]