[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135657,797,1,"单选题","机械设备安装的一般施工程序中，设备基础检查验收的紧后程序是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基础放线",false,{"key":16,"text":17,"correct":14},"B","设备开箱检查",{"key":19,"text":20,"correct":14},"C","安装精度调整与检测",{"key":22,"text":23,"correct":24},"D","垫铁设置",true,"2020版教材P70 \u002F 2019版教材P59 一、机械设备安装的一般程序开箱检查→基础测量放线→基础检查验收→垫铁设置→吊装就位→安装精度调整与检测→设备固定与灌浆→设备装配→润滑与设备加油→试运转。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]