[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135607,797,1,"单选题","下列关于曳引式电梯安装施工程序的表述，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对电梯井道、机房土建工程进行检测鉴定，以确定其位置尺寸是否符合电梯所提供的土建布置图和其他要求",false,{"key":16,"text":17,"correct":18},"B","电梯安装前，建设单位、土建施工单位、降水单位应共同对电梯井道和机房进行检查，对电梯安装条件进行确认",true,{"key":20,"text":21,"correct":14},"C","通电空载试运行合格后负载试运行，并检测各安全装置动作是否正常准确",{"key":23,"text":24,"correct":14},"D","机房设备安装，井道内配管配线","2020版教材P220 \u002F 2019版教材P207 2）电梯安装前，建设单位（或监理单位）、土建施工单位、电梯安装单位应共同对电梯井道和机房进行检查，对电梯安装条件进行确认。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]