[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135601,797,1,"单选题","电梯井道放基准线后的工序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装导轨",true,{"key":16,"text":17,"correct":18},"B","配管配线",false,{"key":20,"text":21,"correct":18},"C","轿厢组装",{"key":23,"text":24,"correct":18},"D","电机安装","2020版教材P220 \u002F 2019版教材P208 井道放基准线后安装导轨等。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]