[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135600":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1135600,797,1,"单选题","安装单位应当在履行告知后、开始施工前，向规定的检验机构申请监督检验。待检验机构（）完毕，并且获悉检验结论为合格后，方可实施安装。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审查电梯制造资料",true,{"key":16,"text":17,"correct":18},"B","参与设备开箱",false,{"key":20,"text":21,"correct":18},"C","审查现场勘测",{"key":23,"text":24,"correct":18},"D","审查各项准备工作","2020版教材P219 \u002F 2019版教材P207 3.安装单位应当在履行告知后、开始施工前（不包括设备开箱、现场勘测等准备工作），向规定的检验机构申请监督检验。待检验机构审查电梯制造资料完毕，并且获悉检验结论为合格后，方可实施安装。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]