[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135569,797,1,"单选题","通风与空调系统调试前应由（）编制系统调试方案并报送监理工程师审核批准。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","建设单位",{"key":22,"text":23,"correct":24},"D","施工单位",true,"2020版教材P202 \u002F 2019版教材P190 1.调试准备（1）通风与空调工程竣工验收的系统调试，应由施工单位负责，监理单位监督，设计单位与建设单位参与和配合。（2）系统调试前应编制调试方案，并应报送专业监理工程师审核批准。系统调试应由专业施工和技术人员实施，调试结束后，应提供完整的调试资料和报告。（3）系统调试所使用的测试仪器应在使用合格检定或校准合格有效期内，精度等级及最小分度值应能满足工程性能测定的要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]