[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135552,797,1,"单选题","在风管漏风量测试施工顺序中，现场测试的紧前工序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风管漏风量抽样方案确定",false,{"key":16,"text":17,"correct":14},"B","风管检查",{"key":19,"text":20,"correct":21},"C","测试仪器仪表检查校准",true,{"key":23,"text":24,"correct":14},"D","现场数据记录","2020版教材P191 \u002F 2019版教材P179 风管漏风量测试施工顺序：风管漏风量抽样方案确定→风管检查→测试仪器仪表检查校准→现场测试→现场数据记录→质量检验。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]