[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135550,797,1,"单选题","下列试验内容，不属于多联机组的冷媒管道试验的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","气密性试验",false,{"key":16,"text":17,"correct":18},"B","气压试验",true,{"key":20,"text":21,"correct":14},"C","真空试验",{"key":23,"text":24,"correct":14},"D","检漏试验","2020版教材P201 \u002F 2019版教材P189 3.制冷剂管道试验要求 （1）制冷剂管道安装完毕，检查合格后，应进行系统管路吹污、气密性试验、真空试验和充注制冷剂检漏试验，技术数据应符合产品技术文件和国家现行标准的有关规定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]