[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135531,797,1,"单选题","接闪带安装要求中，每个固定支架应能承受的垂直拉力是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","19N",false,{"key":16,"text":17,"correct":14},"B","29N",{"key":19,"text":20,"correct":14},"C","39N",{"key":22,"text":23,"correct":24},"D","49N",true,"2020版教材P188 \u002F 2019版教材P177 （2）接闪线和接闪带安装要求：1）接闪线和接闪带安装应平正顺直、无急弯。2）固定支架高度不宜小于150mm,固定支架应间距均匀，支架间距应符合规范的规定。3）每个固定支架应能承受49N的垂直拉力。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]