[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135515,797,1,"单选题","下列施工工序,建筑室内给水管道安装后的工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管道元件检验",false,{"key":16,"text":17,"correct":14},"B","支架安装",{"key":19,"text":20,"correct":21},"C","系统水压试验",true,{"key":23,"text":24,"correct":14},"D","管道测绘放线","2020版教材P168 \u002F 2019版教材P156 室内给水管网施工程序： 1、施工程序：施工准备、预留、预埋，管道测绘放线，管道元件检验，管道支吊架制作 安装，管道加工预制，给水设备安装，管道及配件安装，系统水压试验，防腐绝热，系统清洗消毒。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]