[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1135510,797,1,"单选题","室内隐蔽或埋地的（ ）在隐蔽前必须做灌水试验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","热水管道",false,{"key":16,"text":17,"correct":14},"B","中水管道",{"key":19,"text":20,"correct":14},"C","给水管道",{"key":22,"text":23,"correct":24},"D","排水管道",true,"2020版教材P172 \u002F 2019版教材P161 隐蔽或埋地的排水管道在隐蔽前必须做灌水试验。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]