[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135508":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135508,797,1,"单选题","室内给水工程施工程序：室内给水管道施工程序：施工准备→预留、预埋→管道测绘放线→ 管道元件检验→管道支吊架制作安装→管道加工预制→ 给水设备安装→（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","系统清洗→管道系统试验→防腐绝热",false,{"key":16,"text":17,"correct":14},"B","管道系统试验→系统清洗→防腐绝热",{"key":19,"text":20,"correct":21},"C","管道及配件安装→系统水压试验、防腐绝热→系统清洗、消毒",true,{"key":23,"text":24,"correct":14},"D","防腐绝热→系统清洗→管道系统试验","2020版教材P168 \u002F 2019版教材P156 室内给水管道施工程序:施工准备→预留、预埋→管道测绘放线→管道元件检验→管道支吊架制作安装→管道加工预制→给水设备安装→管道及配件安装→系统水压试验→防腐绝热→系统清洗、消毒。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]