[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135505,797,1,"单选题","下列表述正确的是（ ），",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","排水管道水平干管安装结束后通球率必须达到50%",false,{"key":16,"text":17,"correct":14},"B","通球球径不小于排水管道管径的1\u002F3",{"key":19,"text":20,"correct":21},"C","热水管道系统冲洗时，应先冲洗热水管道底部干管，后冲洗各环路支管",true,{"key":23,"text":24,"correct":14},"D","对于建筑物内不同材质的管道，应先安装塑料管道，后安装钢制管道","2020版教材P170~172 \u002F 2019版教材P159～161 （1）管道安装一般应本着先主管后支管、先上部后下部、先里后外的原则进行安装，对于不同材质的管道应先安装钢质管道，后安装塑料管道，当管道穿过地下室侧墙时应在室内管道安装结束后再进行安装，安装过程应注意成品保护。 （2）进行热水管道系统冲洗时，应先冲洗热水管道底部干管，后冲洗各环路支管 4. 系统通球试验，排水主立管及水平干管管道均应做通球试验，通球球径不小于排水管道管径的2\u002F3，通球率必须达到100%。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]