[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135429":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1135429,797,1,"单选题","吊装系统失稳的主要原因不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","多机吊装不同步",false,{"key":16,"text":17,"correct":18},"B","设计与吊装时受力不一致",true,{"key":20,"text":21,"correct":14},"C","桅杆系统缆风绳、地锚失稳",{"key":23,"text":24,"correct":14},"D","不同起重能力的多机吊装荷载分配不均","2020版教材P52 \u002F 2019版教材P42 吊装系统失稳 1.主要原因：多机吊装不同步，不同起重能力的多机吊装荷载分配不均，多动作、多岗位指挥协调失误，桅杆系统缆风绳、地锚失稳。 2.预防措施：尽量采用同机型起重机、同吊装能力的起重机；集群千斤顶或卷扬机通过计算机控制来实现多吊点同步；通过主、副指挥来实现多机吊装同步；制定周密指挥和操作程序进行演练达到指挥协调一致；缆风绳和地锚严格按吊装方案和工艺计算设置，设置完成后进行检查并做记录。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]