[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135395,797,1,"单选题","长距离输电线路铁塔基础中心桩测定后，一般采用（ ）和平行基线法进行控制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","头尾控制法",false,{"key":16,"text":17,"correct":14},"B","三角法",{"key":19,"text":20,"correct":21},"C","十字线法",true,{"key":23,"text":24,"correct":14},"D","菱形控制法","2020版教材P37 \u002F 2019版教材P27 长距离输电线路钢塔架（ 铁塔）基础施工的测量 中心桩测定后，一般采用十字线法或平行基线法进行控制，控制桩应根据中心桩测定，其允许偏差应符合规定。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]