[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1135386,797,1,"单选题","标高基准点一般埋设在基础的（ ）位置。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最高点",false,{"key":16,"text":17,"correct":14},"B","最低点",{"key":19,"text":20,"correct":21},"C","边缘且便于观察",true,{"key":23,"text":24,"correct":14},"D","纵向中心线","2020版教材P36 \u002F 2019版教材P27 安装标高基准点的测设：标高基准点一般埋设在基础边缘且便于观测的位置。 标高基准点一般有两种： 一种是简单的标高基准点； 另一种是预埋标高基准点。 采用钢制标高基准点，应是靠近设备基础边缘便于测量处， 不允许埋设在设备底板下面的基础表面。",{"id":6,"name":27,"category":28,"favorite":29},"一建机电工程实务","建筑工程",0]