[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-796-29":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":729},{"id":5,"name":6,"category":7,"favorite":8},796,"一建公路工程实务","建筑工程",0,29,50,1523,[13,38,53,68,82,97,111,126,140,154,168,183,197,211,225,239,253,264,278,293,307,321,335,345,360,374,389,404,416,431,445,460,474,488,502,517,532,546,560,573,587,601,615,629,644,658,672,687,701,715],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1135197,2,"多选题","关于桥梁上部结构缆索吊装施工中设置风缆的说法中，不符合设置风缆注意要点的是（ ）。",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","风缆不得布置在水中",true,{"key":24,"text":25,"correct":26},"B","风缆应成对称布置，且上、下游风缆的长度相差不宜过大",false,{"key":28,"text":29,"correct":22},"C","风缆优先采用单线钢丝绳，禁止采用滑轮组",{"key":31,"text":32,"correct":26},"D","对于拱肋为整段吊装或两段吊装的中小跨径双曲拱桥，每孔至少应有一根基肋设置固定的风缆",{"key":34,"text":35,"correct":26},"E","在每孔拱肋全部合龙、横系梁或横隔板达到一定强度后，方可拆除风缆","AC","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},1135198,"缆索吊装施工法中，缆索吊装设备按用途和作用可以分为（ ）等基本部分组成。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"主索",{"key":24,"text":45,"correct":22},"工作索",{"key":28,"text":47,"correct":26},"吊篮",{"key":31,"text":49,"correct":22},"塔架",{"key":34,"text":51,"correct":22},"锚固装置","ABDE",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},1135199,"桥梁上部结构的转体施工按转动方向分为（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":26},"斜向转体施工法",{"key":24,"text":60,"correct":22},"竖向转体施工法",{"key":28,"text":62,"correct":22},"平面转体施工法",{"key":31,"text":64,"correct":26},"空间转体施工法",{"key":34,"text":66,"correct":22},"平竖结合转体法","BCE",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":52,"analysis":37},1135200,"平转施工主要适用于（ ）。",[72,74,76,78,80],{"key":20,"text":73,"correct":22},"刚构梁式桥",{"key":24,"text":75,"correct":22},"斜拉桥",{"key":28,"text":77,"correct":26},"简支梁桥",{"key":31,"text":79,"correct":22},"钢管拱桥",{"key":34,"text":81,"correct":22},"钢筋混凝土拱桥",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":96,"analysis":37},1135202,"挂篮的组成有（ ）。",[86,88,90,92,94],{"key":20,"text":87,"correct":26},"拆除系统",{"key":24,"text":89,"correct":22},"平衡系统及吊杆",{"key":28,"text":91,"correct":22},"锚固",{"key":31,"text":93,"correct":22},"行走系统",{"key":34,"text":95,"correct":22},"主桁架","BCDE",{"id":98,"libraryId":5,"type":15,"typeLabel":16,"stem":99,"options":100,"answer":110,"analysis":37},1135203,"悬臂浇筑法施工刚构桥的挂篮由悬吊系统、行走系统和（ ）组成。",[101,103,105,106,108],{"key":20,"text":102,"correct":26},"满堂支架",{"key":24,"text":104,"correct":26},"拱架",{"key":28,"text":95,"correct":22},{"key":31,"text":107,"correct":22},"工作平台底模架",{"key":34,"text":109,"correct":22},"锚固系与平衡重","CDE",{"id":112,"libraryId":5,"type":15,"typeLabel":16,"stem":113,"options":114,"answer":125,"analysis":37},1135204,"悬臂梁浇筑施工中应注意要点（ ）",[115,117,119,121,123],{"key":20,"text":116,"correct":22},"主梁各部分的长度应充分考虑主梁的形式，跨径，墩宽等来确定",{"key":24,"text":118,"correct":22},"桥墩顶梁段及桥墩附近梁段施工时，可采用托架或膺架为支架就地浇筑混凝土",{"key":28,"text":120,"correct":22},"在梁段混凝土浇筑前，应对挂篮，模板，预应力筋管道，钢筋等接缝处理情况进行全面检查，经确认后方可浇筑",{"key":31,"text":122,"correct":22},"若梁身与墩身采用非刚性连接，为保证结构的稳定性，悬臂梁和连续梁桥应实施0号梁段与桥墩间临时固结支承措施",{"key":34,"text":124,"correct":26},"挂篮安装无须保证安全，稳定、可靠","ABCD",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":125,"analysis":37},1135205,"悬臂浇筑施工法适用于大跨径的（ ）。",[130,132,134,136,138],{"key":20,"text":131,"correct":22},"T型刚构桥",{"key":24,"text":133,"correct":22},"连续刚构桥",{"key":28,"text":135,"correct":22},"预应力混凝土悬臂梁桥",{"key":31,"text":137,"correct":22},"连续梁桥",{"key":34,"text":139,"correct":26},"双曲拱桥",{"id":141,"libraryId":5,"type":15,"typeLabel":16,"stem":142,"options":143,"answer":52,"analysis":37},1135206,"挂篮按结构形式可分为（ ）。",[144,146,148,150,152],{"key":20,"text":145,"correct":22},"桁架式",{"key":24,"text":147,"correct":22},"三角斜拉带式",{"key":28,"text":149,"correct":26},"压重式",{"key":31,"text":151,"correct":22},"预应力束斜拉式",{"key":34,"text":153,"correct":22},"斜拉自锚式",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":96,"analysis":37},1135207,"现浇箱梁支架的布置时，应根据梁截面大小并通过计算确定以确保支架的强度、刚度、稳定性满足要求。计算时除考虑梁体混凝土重量外，还需考虑的因素有（ ）。",[158,160,162,164,166],{"key":20,"text":159,"correct":26},"设计汽车荷载",{"key":24,"text":161,"correct":22},"模板及支架重量",{"key":28,"text":163,"correct":22},"施工荷载（人、料、机等）",{"key":31,"text":165,"correct":22},"作用在模板、支架上的风力",{"key":34,"text":167,"correct":22},"其他可能产生的荷载（如雪荷载，保证设施荷载）",{"id":169,"libraryId":5,"type":15,"typeLabel":16,"stem":170,"options":171,"answer":182,"analysis":37},1135208,"现浇箱梁的模板组成有（ ）。",[172,174,176,178,180],{"key":20,"text":173,"correct":22},"底模",{"key":24,"text":175,"correct":26},"面模",{"key":28,"text":177,"correct":22},"侧模",{"key":31,"text":179,"correct":22},"内模",{"key":34,"text":181,"correct":26},"滑模","ACD",{"id":184,"libraryId":5,"type":15,"typeLabel":16,"stem":185,"options":186,"answer":182,"analysis":37},1135209,"按照加劲梁的支承结构不同悬索桥可分为（ ）悬索桥。",[187,189,191,193,195],{"key":20,"text":188,"correct":22},"单跨两铰加劲梁",{"key":24,"text":190,"correct":26},"两跨两铰加劲梁",{"key":28,"text":192,"correct":22},"三跨连续加劲梁",{"key":31,"text":194,"correct":22},"三跨两铰加劲梁",{"key":34,"text":196,"correct":26},"四跨两铰加劲梁",{"id":198,"libraryId":5,"type":15,"typeLabel":16,"stem":199,"options":200,"answer":52,"analysis":37},1135210,"斜拉桥混凝土主梁的施工方法有（ ）。",[201,203,205,207,209],{"key":20,"text":202,"correct":22},"顶推法",{"key":24,"text":204,"correct":22},"平转法",{"key":28,"text":206,"correct":26},"竖转法",{"key":31,"text":208,"correct":22},"悬臂法",{"key":34,"text":210,"correct":22},"支架法",{"id":212,"libraryId":5,"type":15,"typeLabel":16,"stem":213,"options":214,"answer":182,"analysis":37},1135211,"大跨径劲性拱圈混凝土拱圈（拱肋）的浇筑方法有（ ）。",[215,217,219,221,223],{"key":20,"text":216,"correct":22},"分环多工作面均衡浇筑法",{"key":24,"text":218,"correct":26},"悬臂浇筑法",{"key":28,"text":220,"correct":22},"斜拉扣挂分环连接浇筑法",{"key":31,"text":222,"correct":22},"水箱压载分环浇筑法",{"key":34,"text":224,"correct":26},"悬臂拼装法",{"id":226,"libraryId":5,"type":15,"typeLabel":16,"stem":227,"options":228,"answer":125,"analysis":37},1135212,"钢管混凝土拱桥拱肋安装可采用（ ）。",[229,231,233,235,237],{"key":20,"text":230,"correct":22},"少支架缆索吊装法",{"key":24,"text":232,"correct":22},"无支架缆索吊装法",{"key":28,"text":234,"correct":22},"转体施工法",{"key":31,"text":236,"correct":22},"斜拉扣索悬拼法",{"key":34,"text":238,"correct":26},"满堂式支架法",{"id":240,"libraryId":5,"type":15,"typeLabel":16,"stem":241,"options":242,"answer":125,"analysis":37},1135213,"采用缆索吊装的预制拱肋，必须对（ ）等状况下的拱肋强度进行验算。",[243,245,247,249,251],{"key":20,"text":244,"correct":22},"吊装",{"key":24,"text":246,"correct":22},"搁置",{"key":28,"text":248,"correct":22},"悬挂",{"key":31,"text":250,"correct":22},"安装",{"key":34,"text":252,"correct":26},"临时连接",{"id":254,"libraryId":5,"type":15,"typeLabel":16,"stem":255,"options":256,"answer":263,"analysis":37},1135214,"适用于平转施工的桥梁有（ ）。",[257,258,259,260,262],{"key":20,"text":73,"correct":22},{"key":24,"text":75,"correct":22},{"key":28,"text":81,"correct":22},{"key":31,"text":261,"correct":26},"刚架拱桥",{"key":34,"text":137,"correct":26},"ABC",{"id":265,"libraryId":5,"type":15,"typeLabel":16,"stem":266,"options":267,"answer":125,"analysis":37},1135215,"预防桥头跳车的防治措施包括（ ）。",[268,270,272,274,276],{"key":20,"text":269,"correct":22},"重视桥头地基处理，采用先进的台后填土施工工艺",{"key":24,"text":271,"correct":22},"改善地基性能，提高地基承载力，减少差异沉降",{"key":28,"text":273,"correct":22},"有针对性地选择台后填料，提高桥头路基压实度",{"key":31,"text":275,"correct":22},"做好桥头路堤的排水、防水工程，设置桥头搭板",{"key":34,"text":277,"correct":26},"提高对锚固件焊接施工质量的控制",{"id":279,"libraryId":5,"type":15,"typeLabel":16,"stem":280,"options":281,"answer":292,"analysis":37},1135216,"当混凝土堵塞导管时，可疏通导管内的混凝土的方法有（ ）。",[282,284,286,288,290],{"key":20,"text":283,"correct":26},"拔出导管",{"key":24,"text":285,"correct":22},"用型钢插入导管内来疏通",{"key":28,"text":287,"correct":22},"导管上固定附着式振捣器进行振动",{"key":31,"text":289,"correct":26},"高压水枪喷射",{"key":34,"text":291,"correct":26},"加缓凝剂","BC",{"id":294,"libraryId":5,"type":15,"typeLabel":16,"stem":295,"options":296,"answer":263,"analysis":37},1135217,"由行政部门发布的标准的体系结构层次为两层，一层为门类，包括综合、基础、勘测、设计、检测、施工、监理、养护管理等规范；另一层为专项内容，以下属于门类的有()。",[297,299,301,303,305],{"key":20,"text":298,"correct":22},"基础",{"key":24,"text":300,"correct":22},"勘测",{"key":28,"text":302,"correct":22},"检测",{"key":31,"text":304,"correct":26},"公路砖石与混凝土桥涵设计规范",{"key":34,"text":306,"correct":26},"公路桥涵地基与基础设计规范",{"id":308,"libraryId":5,"type":15,"typeLabel":16,"stem":309,"options":310,"answer":125,"analysis":37},1135218,"分为一级企业和二、三级企业的公路工程施工企业有（ ）。",[311,313,315,317,319],{"key":20,"text":312,"correct":22},"公路路面工程专业承包企业",{"key":24,"text":314,"correct":22},"公路路基工程专业承包企业",{"key":28,"text":316,"correct":22},"桥梁工程专业承包企业",{"key":31,"text":318,"correct":22},"隧道工程专业承包企业",{"key":34,"text":320,"correct":26},"公路工程施工总承包企业",{"id":322,"libraryId":5,"type":15,"typeLabel":16,"stem":323,"options":324,"answer":125,"analysis":37},1135219,"根据国家相关规定，结合公路工程的特点，下列关于公路工程施工总承包企业资质的划分，正确的是（ ）。",[325,327,329,331,333],{"key":20,"text":326,"correct":22},"特级企业",{"key":24,"text":328,"correct":22},"一级企业",{"key":28,"text":330,"correct":22},"二级企业",{"key":31,"text":332,"correct":22},"三级企业",{"key":34,"text":334,"correct":26},"四级企业",{"id":336,"libraryId":5,"type":15,"typeLabel":16,"stem":337,"options":338,"answer":125,"analysis":37},1135220,"（ ）按资质等级划分为一级企业、二级企业、三级企业。",[339,340,341,342,343],{"key":20,"text":316,"correct":22},{"key":24,"text":312,"correct":22},{"key":28,"text":314,"correct":22},{"key":31,"text":318,"correct":22},{"key":34,"text":344,"correct":26},"公路交通工程专业承包企业",{"id":346,"libraryId":5,"type":15,"typeLabel":16,"stem":347,"options":348,"answer":359,"analysis":37},1135221,"可承担单跨100m及以下桥梁工程的施工的企业包括（ ）。",[349,351,353,355,357],{"key":20,"text":350,"correct":22},"公路工程施工总承包特级企业",{"key":24,"text":352,"correct":22},"桥梁工程专业承包一级企业",{"key":28,"text":354,"correct":22},"桥梁工程专业承包二级企业",{"key":31,"text":356,"correct":26},"桥梁工程专业承包三级企业",{"key":34,"text":358,"correct":22},"公路工程施工总承包一级企业","ABCE",{"id":361,"libraryId":5,"type":15,"typeLabel":16,"stem":362,"options":363,"answer":263,"analysis":37},1135222,"二级公路机电工程分项资质承包的工程范围包括（ ）。",[364,366,368,370,372],{"key":20,"text":365,"correct":22},"一级以下公路通信、监控、收费机电系统及配套工程系统的施工及安装",{"key":24,"text":367,"correct":22},"一级以下公路干线传输系统等机电系统及配套工程系统的施工及安装",{"key":28,"text":369,"correct":22},"一级以下公路光（电）缆敷设工程等机电系统及配套工程系统的施工及安装",{"key":31,"text":371,"correct":26},"公路桥梁及隧道工程健康监测机电系统及配套设备的施工及安装",{"key":34,"text":373,"correct":26},"公路桥梁及隧道工程通风、通信管道等机电系统及配套设备的施工及安装",{"id":375,"libraryId":5,"type":15,"typeLabel":16,"stem":376,"options":377,"answer":388,"analysis":37},1135223,"根据交通部《公路工程施工分包管理办法》规定，下列专业分包的说法中错误的有（ ）。",[378,380,382,384,386],{"key":20,"text":379,"correct":22},"分包单位由业主（发包人）或监理人选择",{"key":24,"text":381,"correct":26},"分包合同须事先征得监理人的审批",{"key":28,"text":383,"correct":22},"承包人可以中标后的合同履行期间提出专业分包的申请",{"key":31,"text":385,"correct":22},"若因非分包人原因造成分包人的损失，分包人有权向监理人提出索赔要求",{"key":34,"text":387,"correct":22},"分包人的违约行为承包人可以不需向发包人承担责任","ACDE",{"id":390,"libraryId":5,"type":15,"typeLabel":16,"stem":391,"options":392,"answer":403,"analysis":37},1135224,"承包人未在施工现场设立项目管理机构和派驻相应人员对分包工程的施工活动实施有效管理，并且有下列情形中，属于转包的有（ ）。",[393,395,397,399,401],{"key":20,"text":394,"correct":26},"承包人将工程分包给不具备相应资格的企业或者个人的",{"key":24,"text":396,"correct":26},"分包合同未报发包人备案的",{"key":28,"text":398,"correct":22},"承包人将承包的全部工程发包给他人的",{"key":31,"text":400,"correct":26},"分包人将分包工程再进行分包的",{"key":34,"text":402,"correct":22},"承包人将承包的全部工程肢解后以分包的名义分别发包给他人的","CE",{"id":405,"libraryId":5,"type":15,"typeLabel":16,"stem":406,"options":407,"answer":415,"analysis":37},1135225,"下列叙述行为属于工程转包的有（ ）。",[408,409,410,412,414],{"key":20,"text":398,"correct":22},{"key":24,"text":394,"correct":26},{"key":28,"text":411,"correct":26},"分包人以他人名义承揽分包工程的",{"key":31,"text":413,"correct":26},"承包人将合同文件中明确不得分包的专项工程进行分包的",{"key":34,"text":402,"correct":22},"AE",{"id":417,"libraryId":5,"type":15,"typeLabel":16,"stem":418,"options":419,"answer":430,"analysis":37},1135226,"公路建设市场信用包括公路建设从业单位的（ ）。",[420,422,424,426,428],{"key":20,"text":421,"correct":22},"不良行为信息",{"key":24,"text":423,"correct":22},"表彰奖励类良好行为信息",{"key":28,"text":425,"correct":26},"自有及租赁设备基本情况",{"key":31,"text":427,"correct":26},"资质、资格情况",{"key":34,"text":429,"correct":22},"信用评价信息","ABE",{"id":432,"libraryId":5,"type":15,"typeLabel":16,"stem":433,"options":434,"answer":359,"analysis":37},1135227,"关于公路施工企业信用评价等级的说法正确的有（ ）。 A.公路施工企业信用评价等级分为A A、 A、 B、",[435,437,439,441,443],{"key":20,"text":436,"correct":22},"D五个等级",{"key":24,"text":438,"correct":22},"D级为最低信用等级",{"key":28,"text":440,"correct":22},"AA级为信用好",{"key":31,"text":442,"correct":26},"A级为信用好",{"key":34,"text":444,"correct":22},"C级为信用较差",{"id":446,"libraryId":5,"type":15,"typeLabel":16,"stem":447,"options":448,"answer":459,"analysis":37},1135228,"公路工程设计变更分为（ ）设计变更。",[449,451,453,455,457],{"key":20,"text":450,"correct":26},"特大",{"key":24,"text":452,"correct":22},"重大",{"key":28,"text":454,"correct":22},"较大",{"key":31,"text":456,"correct":22},"一般",{"key":34,"text":458,"correct":26},"轻微","BCD",{"id":461,"libraryId":5,"type":15,"typeLabel":16,"stem":462,"options":463,"answer":125,"analysis":37},1135229,"下列公路工程建设项目中，可以不进行招标的有（ ）。",[464,466,468,470,472],{"key":20,"text":465,"correct":22},"需要采用不可替代的专利或者专有技术",{"key":24,"text":467,"correct":22},"采购人自身具有工程施工或者提供服务的资格和能力，且符合法定要求",{"key":28,"text":469,"correct":22},"涉及国家安全、抢险救灾或者属于利用扶贫资金实行以工代赈、需要使用农民工等特殊情况",{"key":31,"text":471,"correct":22},"已通过招标方式选定的特许经营项目投资人依法能够自行施工或者提供服务",{"key":34,"text":473,"correct":26},"采用公开招标方式的费用占项目合同金额的比例过大的项目",{"id":475,"libraryId":5,"type":15,"typeLabel":16,"stem":476,"options":477,"answer":388,"analysis":37},1135230,"有（ ）情形，招标人应当依照本办法重新招标。",[478,480,482,484,486],{"key":20,"text":479,"correct":22},"少于3个投标人的",{"key":24,"text":481,"correct":26},"投标人未按招标文件要求提交投标保证金",{"key":28,"text":483,"correct":22},"中标人均未与招标人签订公路工程施工合同的",{"key":31,"text":485,"correct":22},"经评标委员会评审，所有投标均不符合招标文件要求的",{"key":34,"text":487,"correct":22},"由于招标人、招标代理人或投标人的违法行为，导致中标无效的",{"id":489,"libraryId":5,"type":15,"typeLabel":16,"stem":490,"options":491,"answer":96,"analysis":37},1135231,"公路工程验收的依据包括（ ）。",[492,494,496,498,500],{"key":20,"text":493,"correct":26},"批准的工程设计、概算、预算文件",{"key":24,"text":495,"correct":22},"批准的工程施工图设计及设计变更文件",{"key":28,"text":497,"correct":22},"招标文件及合同文本",{"key":31,"text":499,"correct":22},"行政主管部门的有关批示文件",{"key":34,"text":501,"correct":22},"批准的可行性研究报告",{"id":503,"libraryId":5,"type":15,"typeLabel":16,"stem":504,"options":505,"answer":516,"analysis":37},1135232,"公路工程建设项目验收分为（ ）。",[506,508,510,512,514],{"key":20,"text":507,"correct":26},"中间交工验收",{"key":24,"text":509,"correct":22},"交工验收",{"key":28,"text":511,"correct":26},"工序验收",{"key":31,"text":513,"correct":22},"竣工验收",{"key":34,"text":515,"correct":26},"工程质量验收","BD",{"id":518,"libraryId":5,"type":15,"typeLabel":16,"stem":519,"options":520,"answer":531,"analysis":37},1135233,"公路工程交工验收必须具备以下条件（ ）。",[521,523,525,527,529],{"key":20,"text":522,"correct":22},"监理工程师对工程质量的评定合格",{"key":24,"text":524,"correct":22},"施工单位、监理单位已完成本合同段的工作总结",{"key":28,"text":526,"correct":26},"施工、监理、设计、建设、监督等单位已编写完成汇报材料",{"key":31,"text":528,"correct":22},"质量监督机构按交通部规定的公路工程质量鉴定办法对工程质量进行检测，并出具检测意见",{"key":34,"text":530,"correct":26},"按规定已编制好工程竣工决算","ABD",{"id":533,"libraryId":5,"type":15,"typeLabel":16,"stem":534,"options":535,"answer":52,"analysis":37},1135234,"公路工程竣工验收应具备的条件包括（ ）。",[536,538,540,542,544],{"key":20,"text":537,"correct":22},"经过交工验收各标段均达到合格以上的工程",{"key":24,"text":539,"correct":22},"按国家《基本建设项目档案资料管理暂行规定》和相关要求已编制完成竣工文件",{"key":28,"text":541,"correct":26},"按规定开始编制工程竣工决算",{"key":31,"text":543,"correct":22},"施工,监理,设计,建设.监督等单位已编写完成汇报材料",{"key":34,"text":545,"correct":22},"对未完工程或交工验收时提出的修复,补救工程已处理完毕，并经监理工程师和质量监督部门检验合格",{"id":547,"libraryId":5,"type":15,"typeLabel":16,"stem":548,"options":549,"answer":359,"analysis":37},1135235,"交工验收和竣工验收应听取和审议的报告有（ ）。",[550,552,554,556,558],{"key":20,"text":551,"correct":22},"建设单位关于项目执行情况的报告",{"key":24,"text":553,"correct":22},"施工单位关于工程施工情况的报告",{"key":28,"text":555,"correct":22},"监理单位关于工程监理情况的报告",{"key":31,"text":557,"correct":26},"质量监督部门关于工程质量监督工作的报告",{"key":34,"text":559,"correct":22},"设计单位关于设计情况的报告",{"id":561,"libraryId":5,"type":15,"typeLabel":16,"stem":562,"options":563,"answer":388,"analysis":37},1135236,"根据《公路水运工程安全生产监督管理办法》（交通运输部令2017年第25号），（ ）在投入使用前，应当组织有关单位进行验收，或者委托具有相应资质的检验检测机构进行验收，验收合格后方可使用。",[564,566,568,570,571],{"key":20,"text":565,"correct":22},"翻模",{"key":24,"text":567,"correct":26},"施工测量仪器",{"key":28,"text":569,"correct":22},"挂篮",{"key":31,"text":181,"correct":22},{"key":34,"text":572,"correct":22},"爬模",{"id":574,"libraryId":5,"type":15,"typeLabel":16,"stem":575,"options":576,"answer":182,"analysis":37},1135237,"生产安全事故等级的划分指标有（ ）。",[577,579,581,583,585],{"key":20,"text":578,"correct":22},"死亡人数",{"key":24,"text":580,"correct":26},"间接经济损失",{"key":28,"text":582,"correct":22},"直接经济损失",{"key":31,"text":584,"correct":22},"重伤人数",{"key":34,"text":586,"correct":26},"轻伤人数",{"id":588,"libraryId":5,"type":15,"typeLabel":16,"stem":589,"options":590,"answer":292,"analysis":37},1135238,"根据交通运输部颁布的《公路水运建设工程质量事故等级划分和报告制度》（交办安监[2016]146号），下列属于公路工程一般质量事故的是()。",[591,593,595,597,599],{"key":20,"text":592,"correct":26},"特长隧道结构坍塌",{"key":24,"text":594,"correct":22},"造成直接经济损失在100万元以上1000万元以下",{"key":28,"text":596,"correct":22},"除高速公路以外的公路项目中桥或大桥主体结构垮塌",{"key":31,"text":598,"correct":26},"造成直接经济损失在1000万元以上5000万元以下",{"key":34,"text":600,"correct":26},"造成2人死亡的",{"id":602,"libraryId":5,"type":15,"typeLabel":16,"stem":603,"options":604,"answer":263,"analysis":37},1135239,"根据工程技术档案管理的要求，工程完工验收后，施工单位应交建设单位保管的资料有（ ）。2013年",[605,607,609,611,613],{"key":20,"text":606,"correct":22},"竣工图表",{"key":24,"text":608,"correct":22},"隐蔽工程验收记录",{"key":28,"text":610,"correct":22},"永久性水准点的位置",{"key":31,"text":612,"correct":26},"施工经验总结",{"key":34,"text":614,"correct":26},"施工日记",{"id":616,"libraryId":5,"type":15,"typeLabel":16,"stem":617,"options":618,"answer":52,"analysis":37},1135240,"热拌沥青混合料配合比设计应通过目标配合比设计、配合比设计及生产配合比验证三个阶段以确定沥青混合料的（ ）2016年",[619,621,623,625,627],{"key":20,"text":620,"correct":22},"材料品种",{"key":24,"text":622,"correct":22},"配合比",{"key":28,"text":624,"correct":26},"渗水系数",{"key":31,"text":626,"correct":22},"矿料级配",{"key":34,"text":628,"correct":22},"最佳沥青用量",{"id":630,"libraryId":5,"type":15,"typeLabel":16,"stem":631,"options":632,"answer":643,"analysis":37},1135241,"下列斜拉桥混凝土索塔质量检验实测项目中，属于关键项目的有（ ）。2017真题",[633,635,637,639,641],{"key":20,"text":634,"correct":22},"混凝土强度",{"key":24,"text":636,"correct":26},"塔柱底偏位",{"key":28,"text":638,"correct":22},"倾斜度",{"key":31,"text":640,"correct":26},"锚固点高程",{"key":34,"text":642,"correct":22},"孔道位置","ACE",{"id":645,"libraryId":5,"type":15,"typeLabel":16,"stem":646,"options":647,"answer":531,"analysis":37},1135242,"下列内容中，属于施工总体部署主要内容的有（）。2018真题",[648,650,652,654,656],{"key":20,"text":649,"correct":22},"建立施工管理机构",{"key":24,"text":651,"correct":22},"划分施工任务",{"key":28,"text":653,"correct":26},"编制施工进度计划",{"key":31,"text":655,"correct":22},"确定施工顺序",{"key":34,"text":657,"correct":26},"制定各项资源需求计划",{"id":659,"libraryId":5,"type":15,"typeLabel":16,"stem":660,"options":661,"answer":359,"analysis":37},1135243,"下列检测项目中，属于石方路基实测项目的有（ ）。2014年",[662,664,666,668,670],{"key":20,"text":663,"correct":22},"平整度",{"key":24,"text":665,"correct":22},"平顺度",{"key":28,"text":667,"correct":22},"弯沉值",{"key":31,"text":669,"correct":26},"强度",{"key":34,"text":671,"correct":22},"纵断高程",{"id":673,"libraryId":5,"type":15,"typeLabel":16,"stem":674,"options":675,"answer":686,"analysis":37},1135244,"关于安全带使用说法，正确的有（ ）2016年",[676,678,680,682,684],{"key":20,"text":677,"correct":26},"安全带应低挂高用",{"key":24,"text":679,"correct":26},"安全带的安全绳与悬吊绳应共用连接器",{"key":28,"text":681,"correct":26},"安全带的安全绳可作为悬吊绳",{"key":31,"text":683,"correct":22},"安全带的安全绳严禁打结使用",{"key":34,"text":685,"correct":22},"安全带的安全绳上严禁挂钩","DE",{"id":688,"libraryId":5,"type":15,"typeLabel":16,"stem":689,"options":690,"answer":67,"analysis":37},1135245,"在生产事故应急救援预案中，应急响应分级的依据主要有（ ）。2013年",[691,693,695,697,699],{"key":20,"text":692,"correct":26},"事故发生所在地行政区域",{"key":24,"text":694,"correct":22},"事故危害程度",{"key":28,"text":696,"correct":22},"事故影响范围",{"key":31,"text":698,"correct":26},"发生事故的工程合同金额",{"key":34,"text":700,"correct":22},"事故单位控制事态的能力",{"id":702,"libraryId":5,"type":15,"typeLabel":16,"stem":703,"options":704,"answer":359,"analysis":37},1135246,"关于隧道施工爆破作业安全技术要求说法，正确的有（ ）2016年",[705,707,709,711,713],{"key":20,"text":706,"correct":22},"洞内爆破必须统一指挥，由专业人员进行作业",{"key":24,"text":708,"correct":22},"爆破加工房应设在洞口50m 以外的安全地点",{"key":28,"text":710,"correct":22},"发现有“盲炮”时，必须由原爆破人员按规定处理",{"key":31,"text":712,"correct":26},"可用自卸汽车运送爆破器材",{"key":34,"text":714,"correct":22},"装炮时，应使用木质炮棍装药，严禁火种",{"id":716,"libraryId":5,"type":15,"typeLabel":16,"stem":717,"options":718,"answer":52,"analysis":37},1135247,"根据《公路工程标准施工招标文件》，下列各项构成合同文件的有（ ）。2015年",[719,721,723,725,727],{"key":20,"text":720,"correct":22},"合同协议书及各种合同附件",{"key":24,"text":722,"correct":22},"投标函及投标函附录",{"key":28,"text":724,"correct":26},"招标文件",{"key":31,"text":726,"correct":22},"中标通知书",{"key":34,"text":728,"correct":22},"已标价工程量清单",[730,734,737,740,743,746],{"id":731,"name":732,"category":7,"favorite":733},1,"领导干部任职前廉政法规知识测试题",92,{"id":735,"name":736,"category":7,"favorite":731},595,"建筑结构与设备",{"id":738,"name":739,"category":7,"favorite":731},715,"招标采购专业知识与法律法规",{"id":741,"name":742,"category":7,"favorite":731},848,"市政方向-通用基础",{"id":744,"name":745,"category":7,"favorite":8},534,"BIM工程师",{"id":747,"name":745,"category":7,"favorite":8},535]