[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-796-17":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":598},{"id":5,"name":6,"category":7,"favorite":8},796,"一建公路工程实务","建筑工程",0,17,50,1523,[13,34,46,58,70,82,94,106,118,130,142,150,162,174,184,196,208,220,232,244,256,265,277,289,300,312,324,336,348,360,372,384,396,408,420,432,444,456,468,479,491,503,514,522,530,538,550,562,574,586],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},1134563,1,"单选题","关于钢筋混凝土梁桥施工时对于预拱度偏差防治的说法错误的是（ ）。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","支架基础应符合设计要求",false,{"key":24,"text":25,"correct":22},"B","预应力波纹管管道的安装定位应准确",{"key":27,"text":28,"correct":29},"C","控制预应力张拉的混凝土试块应采取标准养护",true,{"key":31,"text":32,"correct":22},"D","预制梁存梁时间不宜过长","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":31,"analysis":33},1134564,"钻孔灌注桩施工中，为满足混凝土和易性要求，坍落度应控制在（ ）cm范围内。",[38,40,42,44],{"key":20,"text":39,"correct":22},"8～12",{"key":24,"text":41,"correct":22},"10～15",{"key":27,"text":43,"correct":22},"12～16",{"key":31,"text":45,"correct":29},"18～22",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},1134565,"钻孔灌注桩断桩的防治措施错误的是（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"混凝土坍落度要控制在18～22cm",{"key":24,"text":53,"correct":22},"若灌注时间较长时，可以在混凝土中加入缓凝剂",{"key":27,"text":55,"correct":22},"下导管时，其底口距孔底的距离控制在25～40cm",{"key":31,"text":57,"correct":29},"导管的埋置深度一般控制在1.5m左右",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},1134566,"钻孔灌注桩施工时，导管使用前，要对导管进行检漏和（ ），以防导管渗漏。",[62,64,66,68],{"key":20,"text":63,"correct":22},"抗压试验",{"key":24,"text":65,"correct":29},"抗拉力试验",{"key":27,"text":67,"correct":22},"抗弯试验",{"key":31,"text":69,"correct":22},"抗折试验",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":27,"analysis":33},1134567,"公路建设管理法规体系是梯形，分为()。",[74,76,78,80],{"key":20,"text":75,"correct":22},"一级五层次",{"key":24,"text":77,"correct":22},"二级二层次",{"key":27,"text":79,"correct":29},"二级五层次",{"key":31,"text":81,"correct":22},"五级五层次",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":27,"analysis":33},1134568,"竣工验收质量评定中，工程质量评定得分大于等于（ ）分为优良。",[86,88,90,92],{"key":20,"text":87,"correct":22},"80",{"key":24,"text":89,"correct":22},"85",{"key":27,"text":91,"correct":29},"90",{"key":31,"text":93,"correct":22},"95",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":20,"analysis":33},1134569,"按《公路工程质量检验评定标准》的要求,项目在竣工验收时综合评价为优良的必要条件是（ ）。",[98,100,102,104],{"key":20,"text":99,"correct":29},"质量评定大于等于90分",{"key":24,"text":101,"correct":22},"项目法人工作评价大于等于90分",{"key":27,"text":103,"correct":22},"施工单位工作评价大于等于90分",{"key":31,"text":105,"correct":22},"监理工作评价大于等于90分",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":31,"analysis":33},1134570,"公路工程施工企业资质等级不包括（ ）。",[110,112,114,116],{"key":20,"text":111,"correct":22},"一级公路工程施工总承包",{"key":24,"text":113,"correct":22},"三级路面工程专业承包",{"key":27,"text":115,"correct":22},"三级桥梁工程专业承包",{"key":31,"text":117,"correct":29},"通信、收费综合系统工程分项承包",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":31,"analysis":33},1134571,"结合公路工程建设特点，公路工程施工企业分为（ ）。",[122,124,126,128],{"key":20,"text":123,"correct":22},"三类",{"key":24,"text":125,"correct":22},"四类",{"key":27,"text":127,"correct":22},"五类",{"key":31,"text":129,"correct":29},"六类",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":27,"analysis":33},1134572,"公路工程施工总承包企业资质可一共分为（ ）。",[134,136,138,140],{"key":20,"text":135,"correct":22},"二级",{"key":24,"text":137,"correct":22},"三级",{"key":27,"text":139,"correct":29},"四级",{"key":31,"text":141,"correct":22},"五级",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":24,"analysis":33},1134573,"公路路面工程专业承包企业资质可一共分为（ ）。",[146,147,148,149],{"key":20,"text":135,"correct":22},{"key":24,"text":137,"correct":29},{"key":27,"text":139,"correct":22},{"key":31,"text":141,"correct":22},{"id":151,"libraryId":5,"type":15,"typeLabel":16,"stem":152,"options":153,"answer":20,"analysis":33},1134574,"隧道工程专业承包企业分为（ ）。",[154,156,158,160],{"key":20,"text":155,"correct":29},"一级企业、二级企业、三级企业",{"key":24,"text":157,"correct":22},"特级企业，一级企业",{"key":27,"text":159,"correct":22},"特级企业，一级企业、二级企业、三级企业",{"key":31,"text":161,"correct":22},"特级企业，一级企业、二级企业",{"id":163,"libraryId":5,"type":15,"typeLabel":16,"stem":164,"options":165,"answer":27,"analysis":33},1134575,"根据国家相关规定，可承担各级公路及其桥梁、长度在3000m以下的隧道工程的施工总承包的企业是（ ）。",[166,168,170,172],{"key":20,"text":167,"correct":22},"施工总承包三级",{"key":24,"text":169,"correct":22},"施工总承包二级",{"key":27,"text":171,"correct":29},"施工总承包一级",{"key":31,"text":173,"correct":22},"施工专业承包二级资质",{"id":175,"libraryId":5,"type":15,"typeLabel":16,"stem":176,"options":177,"answer":31,"analysis":33},1134576,"根据国家相关规定，可承担各等级公路及其桥梁、隧道工程施工的企业是（ ）。",[178,179,180,182],{"key":20,"text":137,"correct":22},{"key":24,"text":135,"correct":22},{"key":27,"text":181,"correct":22},"一级",{"key":31,"text":183,"correct":29},"特级",{"id":185,"libraryId":5,"type":15,"typeLabel":16,"stem":186,"options":187,"answer":24,"analysis":33},1134577,"可承担各类桥梁工程的施工企业是（ ）。",[188,190,192,194],{"key":20,"text":189,"correct":22},"桥梁工程专业承包特级企业",{"key":24,"text":191,"correct":29},"桥梁工程专业承包一级企业",{"key":27,"text":193,"correct":22},"桥梁工程专业承包二级企业",{"key":31,"text":195,"correct":22},"桥梁工程专业承包三级企业",{"id":197,"libraryId":5,"type":15,"typeLabel":16,"stem":198,"options":199,"answer":31,"analysis":33},1134578,"下列工程任务不得分包的是（ ）。",[200,202,204,206],{"key":20,"text":201,"correct":22},"勘察工作",{"key":24,"text":203,"correct":22},"设计工作",{"key":27,"text":205,"correct":22},"施工工作",{"key":31,"text":207,"correct":29},"监理工作",{"id":209,"libraryId":5,"type":15,"typeLabel":16,"stem":210,"options":211,"answer":31,"analysis":33},1134579,"具有劳务用工主体资格的是（ ）。",[212,214,216,218],{"key":20,"text":213,"correct":22},"项目经理",{"key":24,"text":215,"correct":22},"项目经理部",{"key":27,"text":217,"correct":22},"施工班组",{"key":31,"text":219,"correct":29},"承包人",{"id":221,"libraryId":5,"type":15,"typeLabel":16,"stem":222,"options":223,"answer":24,"analysis":33},1134580,"分包工程中的关系是（ ）。",[224,226,228,230],{"key":20,"text":225,"correct":22},"发包人与分包人有合同关系",{"key":24,"text":227,"correct":29},"承包人与分包人有合同关系",{"key":27,"text":229,"correct":22},"监理人与分包人有合同关系",{"key":31,"text":231,"correct":22},"监理人与分包人有监理关系",{"id":233,"libraryId":5,"type":15,"typeLabel":16,"stem":234,"options":235,"answer":24,"analysis":33},1134581,"项目所在地省级交通主管部门评定的最高信用等级是（ ）。",[236,238,240,242],{"key":20,"text":237,"correct":22},"单A",{"key":24,"text":239,"correct":29},"双A",{"key":27,"text":241,"correct":22},"三A",{"key":31,"text":243,"correct":22},"四A",{"id":245,"libraryId":5,"type":15,"typeLabel":16,"stem":246,"options":247,"answer":20,"analysis":33},1134582,"下列属于公路建设市场信用信息中最高信用等级的是（ ）。",[248,250,252,254],{"key":20,"text":249,"correct":29},"AA级",{"key":24,"text":251,"correct":22},"A级",{"key":27,"text":253,"correct":22},"B级",{"key":31,"text":255,"correct":22},"D级",{"id":257,"libraryId":5,"type":15,"typeLabel":16,"stem":258,"options":259,"answer":20,"analysis":33},1134583,"下列级别中，不属于全国公路建设从业单位信用评价等级的是（ ）。",[260,262,263,264],{"key":20,"text":261,"correct":29},"E级",{"key":24,"text":249,"correct":22},{"key":27,"text":255,"correct":22},{"key":31,"text":253,"correct":22},{"id":266,"libraryId":5,"type":15,"typeLabel":16,"stem":267,"options":268,"answer":31,"analysis":33},1134584,"关于公路设计变更的说法，正确的是（ ）。",[269,271,273,275],{"key":20,"text":270,"correct":22},"公路工程设计变更分为重大设计变更、较大设计变更和较小设计变更",{"key":24,"text":272,"correct":22},"公路工程重大、较大设计变更实行审批制。经批准的设计变更最多不得变更3次",{"key":27,"text":274,"correct":22},"公路工程勘察设计及监理等单位才可以向项目法人提出公路工程设计变更的建议",{"key":31,"text":276,"correct":29},"由于公路施工有关单位的过失引起公路工程设计变更并造成损失的，施工单位应当承担相应的费用和相关责任",{"id":278,"libraryId":5,"type":15,"typeLabel":16,"stem":279,"options":280,"answer":24,"analysis":33},1134585,"以下设计变更不属于较大设计变更范畴的是（ ）。",[281,283,285,287],{"key":20,"text":282,"correct":22},"超过施工图设计批准预算",{"key":24,"text":284,"correct":29},"收费方式及站点位置、规模发生变化",{"key":27,"text":286,"correct":22},"单项工程费用变化超过500万元的变更",{"key":31,"text":288,"correct":22},"隧道的数量或方案发生变化",{"id":290,"libraryId":5,"type":15,"typeLabel":16,"stem":291,"options":292,"answer":20,"analysis":33},1134586,"以下设计变更属于重大设计变更范畴的是（ ）。",[293,295,297,298],{"key":20,"text":294,"correct":29},"超过初步设计批准概算",{"key":24,"text":296,"correct":22},"连续长度2公里以上（10公里以下）的路线方案调整",{"key":27,"text":286,"correct":22},{"key":31,"text":299,"correct":22},"变更路面结构类型、宽度和厚度",{"id":301,"libraryId":5,"type":15,"typeLabel":16,"stem":302,"options":303,"answer":24,"analysis":33},1134587,"按《公路工程设计变更管理办法》的要求，重大设计变更由（ ）负责审批。",[304,306,308,310],{"key":20,"text":305,"correct":22},"国务院",{"key":24,"text":307,"correct":29},"交通部",{"key":27,"text":309,"correct":22},"交通厅",{"key":31,"text":311,"correct":22},"设计院",{"id":313,"libraryId":5,"type":15,"typeLabel":16,"stem":314,"options":315,"answer":20,"analysis":33},1134588,"对于公路工程中出现的一般设计变更的审查，应由（ ）负责。",[316,318,320,322],{"key":20,"text":317,"correct":29},"建设单位",{"key":24,"text":319,"correct":22},"设计单位",{"key":27,"text":321,"correct":22},"监理单位",{"key":31,"text":323,"correct":22},"交通行政主管部门",{"id":325,"libraryId":5,"type":15,"typeLabel":16,"stem":326,"options":327,"answer":27,"analysis":33},1134589,"《公路工程建设项目招标投标管理办法》规定，公路工程建设项目履行项目审批或者核准手续后，方可开展勘察设计招标：（ ），方可开展施工监理、设计施丁总承包招标。",[328,330,332,334],{"key":20,"text":329,"correct":22},"施工图设计文件批准后",{"key":24,"text":331,"correct":22},"可行性研究文件批准后",{"key":27,"text":333,"correct":29},"初步设计文件批准后",{"key":31,"text":335,"correct":22},"施工许可证办理后",{"id":337,"libraryId":5,"type":15,"typeLabel":16,"stem":338,"options":339,"answer":20,"analysis":33},1134590,"公开招标与邀请招标在招标程序上的主要不同是（ ）。",[340,342,344,346],{"key":20,"text":341,"correct":29},"是否进行资格预审",{"key":24,"text":343,"correct":22},"是否组织现场考察",{"key":27,"text":345,"correct":22},"是否公开开标",{"key":31,"text":347,"correct":22},"是否解答投标单位的质疑",{"id":349,"libraryId":5,"type":15,"typeLabel":16,"stem":350,"options":351,"answer":24,"analysis":33},1134591,"公路工程招投标过程中，招标人和中标人应当自中标通知书发出之日起（ ）日内订立书面公路工程施工合同。",[352,354,356,358],{"key":20,"text":353,"correct":22},"15",{"key":24,"text":355,"correct":29},"30",{"key":27,"text":357,"correct":22},"14",{"key":31,"text":359,"correct":22},"28",{"id":361,"libraryId":5,"type":15,"typeLabel":16,"stem":362,"options":363,"answer":31,"analysis":33},1134592,"不属于公路工程交工验收应具备的条件的是（ ）。",[364,366,368,370],{"key":20,"text":365,"correct":22},"监理工程师对工程质量评定合格",{"key":24,"text":367,"correct":22},"监督机构对工程进行了检测",{"key":27,"text":369,"correct":22},"监理单位已完成工作总结",{"key":31,"text":371,"correct":29},"已通车试运营二年",{"id":373,"libraryId":5,"type":15,"typeLabel":16,"stem":374,"options":375,"answer":20,"analysis":33},1134593,"公路工程竣工验收的主要目的是综合评价（ ）。",[376,378,380,382],{"key":20,"text":377,"correct":29},"工程建设成果",{"key":24,"text":379,"correct":22},"施工合同履行情况",{"key":27,"text":381,"correct":22},"投资落实情况",{"key":31,"text":383,"correct":22},"技术标准执行情况",{"id":385,"libraryId":5,"type":15,"typeLabel":16,"stem":386,"options":387,"answer":27,"analysis":33},1134594,"由建设单位主持，检查施工合同的执行情况，评价工程质量是否符合技术标准及设计要求，是否可以移交下一阶段施工称为（ ）。",[388,390,392,394],{"key":20,"text":389,"correct":22},"竣工验收",{"key":24,"text":391,"correct":22},"中间交工验收",{"key":27,"text":393,"correct":29},"交工验收",{"key":31,"text":395,"correct":22},"工序验收",{"id":397,"libraryId":5,"type":15,"typeLabel":16,"stem":398,"options":399,"answer":31,"analysis":33},1134595,"竣工验收阶段，其主要工作是对工程质量、参见单位和建设项目进行综合评价，并（ ）。",[400,402,404,406],{"key":20,"text":401,"correct":22},"检查施工合同的执行情况",{"key":24,"text":403,"correct":22},"对各参建单位工作进行初步评价",{"key":27,"text":405,"correct":22},"评价工程质量是否满足通车要求",{"key":31,"text":407,"correct":29},"对工程建设项目做出整体性综合评价",{"id":409,"libraryId":5,"type":15,"typeLabel":16,"stem":410,"options":411,"answer":24,"analysis":33},1134596,"公路工程竣工验收具备的条件中，应通车试运营（ ）年以上。",[412,414,416,418],{"key":20,"text":413,"correct":22},"1",{"key":24,"text":415,"correct":29},"2",{"key":27,"text":417,"correct":22},"3",{"key":31,"text":419,"correct":22},"4",{"id":421,"libraryId":5,"type":15,"typeLabel":16,"stem":422,"options":423,"answer":20,"analysis":33},1134597,"按《公路工程质量检验评定标准》JTGF80\u002F1-2004进行质量评定时，交工验收工程质量等级评定分（ ）。",[424,426,428,430],{"key":20,"text":425,"correct":29},"合格、不合格",{"key":24,"text":427,"correct":22},"优良、中、不合格",{"key":27,"text":429,"correct":22},"优良、合格、不合格",{"key":31,"text":431,"correct":22},"中、不合格",{"id":433,"libraryId":5,"type":15,"typeLabel":16,"stem":434,"options":435,"answer":31,"analysis":33},1134599,"施工单位应当取得安全生产许可证，施工单位的（ ）必须取得考核合格证书，方可参加公路水运工程投标及施工。",[436,438,440,442],{"key":20,"text":437,"correct":22},"主要负责人、项目负责人、兼职安全生产管理人员",{"key":24,"text":439,"correct":22},"财务负责人、项目负责人、专项安全生产管理人员",{"key":27,"text":441,"correct":22},"主要负责人、专项安全生产管理人员、兼职安全生产管理人员",{"key":31,"text":443,"correct":29},"主要负责人、项目负责人、专项安全生产管理人员",{"id":445,"libraryId":5,"type":15,"typeLabel":16,"stem":446,"options":447,"answer":27,"analysis":33},1134600,"关于公路桥梁和隧道工程安全风险评估相关要求的说法错误的是（ ）。",[448,450,452,454],{"key":20,"text":449,"correct":22},"施工安全风险评估范围，与由各地工程建设条件、技术复杂程度有关",{"key":24,"text":451,"correct":22},"多跨或跨径大于40m的石拱桥应进行施工风险评估",{"key":27,"text":453,"correct":29},"桥梁拆除工程可以不进行施工风险评估",{"key":31,"text":455,"correct":22},"墩高或净空大于100m的桥梁工程应进行施工风险评估",{"id":457,"libraryId":5,"type":15,"typeLabel":16,"stem":458,"options":459,"answer":27,"analysis":33},1134601,"总体风险评估等级达到（ ）及以上工程应进行专项风险评估。其他风险等级的可视情况开展专项风险评估。",[460,462,464,466],{"key":20,"text":461,"correct":22},"I级",{"key":24,"text":463,"correct":22},"Ⅱ级",{"key":27,"text":465,"correct":29},"Ⅲ级",{"key":31,"text":467,"correct":22},"Ⅲ级及以上",{"id":469,"libraryId":5,"type":15,"typeLabel":16,"stem":470,"options":471,"answer":24,"analysis":33},1134602,"根据《公路桥梁和隧道工程施工安全风险评估指南（试行）》的规定，当桥梁或隧道工程总体风险评估等级达到（ ）及以上时，应进行专项风险评估。",[472,474,475,477],{"key":20,"text":473,"correct":22},"Ⅰ级",{"key":24,"text":465,"correct":29},{"key":27,"text":476,"correct":22},"Ⅳ级",{"key":31,"text":478,"correct":22},"Ⅴ级",{"id":480,"libraryId":5,"type":15,"typeLabel":16,"stem":481,"options":482,"answer":31,"analysis":33},1134603,"当专项风险等级为（ ）级且无法降低时，必须提高现场防护标准，并视情况开展第三方施工监测。",[483,485,487,489],{"key":20,"text":484,"correct":22},"Ⅰ",{"key":24,"text":486,"correct":22},"Ⅱ",{"key":27,"text":488,"correct":22},"Ⅲ",{"key":31,"text":490,"correct":29},"Ⅳ",{"id":492,"libraryId":5,"type":15,"typeLabel":16,"stem":493,"options":494,"answer":24,"analysis":33},1134604,"某工程事故造成3人死亡，10人重伤，直接经济损失达2000万元，根据《生产安全事故报告和调查处理条例》，该事故等级为（ ）。",[495,497,499,501],{"key":20,"text":496,"correct":22},"特别重大事故",{"key":24,"text":498,"correct":29},"较大事故",{"key":27,"text":500,"correct":22},"重大事故",{"key":31,"text":502,"correct":22},"一般事故",{"id":504,"libraryId":5,"type":15,"typeLabel":16,"stem":505,"options":506,"answer":27,"analysis":33},1134605,"安全事故自发生之日起（ ）日内，事故造成的伤亡人数发生变化的，应当及时补报。",[507,509,511,512],{"key":20,"text":508,"correct":22},"10",{"key":24,"text":510,"correct":22},"20",{"key":27,"text":355,"correct":29},{"key":31,"text":513,"correct":22},"40",{"id":515,"libraryId":5,"type":15,"typeLabel":16,"stem":516,"options":517,"answer":24,"analysis":33},1134606,"某项目施工中因某次事故死亡10人，则该事故属于（ ）。",[518,519,520,521],{"key":20,"text":496,"correct":22},{"key":24,"text":500,"correct":29},{"key":27,"text":498,"correct":22},{"key":31,"text":502,"correct":22},{"id":523,"libraryId":5,"type":15,"typeLabel":16,"stem":524,"options":525,"answer":27,"analysis":33},1134607,"根据《生产安全事故报告和调查处理条例》的有关规定，除道路交通事故、火灾事故外，自事故发生之日起（ ）日内，事故造成的伤亡人数发生变化的，应当及时补报。",[526,527,528,529],{"key":20,"text":353,"correct":22},{"key":24,"text":510,"correct":22},{"key":27,"text":355,"correct":29},{"key":31,"text":513,"correct":22},{"id":531,"libraryId":5,"type":15,"typeLabel":16,"stem":532,"options":533,"answer":24,"analysis":33},1134608,"根据《公路水运工程质量监督管理规定》（交通运输部令2017年第28号），建设单位提交的材料符合规定的，交通运输主管部门或者其委托的建设工程质量监督机构应当在()个工作日内为其办理工程质量监督手续，出具公路水运工程质量监督管理受理通知书。",[534,535,536,537],{"key":20,"text":508,"correct":22},{"key":24,"text":353,"correct":29},{"key":27,"text":510,"correct":22},{"key":31,"text":355,"correct":22},{"id":539,"libraryId":5,"type":15,"typeLabel":16,"stem":540,"options":541,"answer":24,"analysis":33},1134610,"根据流水施工组织原理，异步距异节拍流水实质上是按无节拍流水组织，引用流水步距概念目的的就是为了（ ）。2016年",[542,544,546,548],{"key":20,"text":543,"correct":22},"计算流水工期",{"key":24,"text":545,"correct":29},"消除流水施工中存在的窝工现象",{"key":27,"text":547,"correct":22},"统计资源需要量",{"key":31,"text":549,"correct":22},"分析流水强度",{"id":551,"libraryId":5,"type":15,"typeLabel":16,"stem":552,"options":553,"answer":24,"analysis":33},1134611,"（2020年真题）关于施工段落的划分，错误的是（ ）",[554,556,558,560],{"key":20,"text":555,"correct":22},"各段落之间工程量基本平衡",{"key":24,"text":557,"correct":29},"尽可能化整为零",{"key":27,"text":559,"correct":22},"避免造成段落之间的施工干扰",{"key":31,"text":561,"correct":22},"保持构造物的完整性",{"id":563,"libraryId":5,"type":15,"typeLabel":16,"stem":564,"options":565,"answer":27,"analysis":33},1134612,"隧道衬砌裂缝形成的原因不包括（）。2018真题",[566,568,570,572],{"key":20,"text":567,"correct":22},"围岩压力不均",{"key":24,"text":569,"correct":22},"衬砌背后有空洞",{"key":27,"text":571,"correct":29},"钢筋保护层厚度大于3cm",{"key":31,"text":573,"correct":22},"衬砌厚度严重不足",{"id":575,"libraryId":5,"type":15,"typeLabel":16,"stem":576,"options":577,"answer":24,"analysis":33},1134613,"关于工程进度曲线（“S”曲线）特点的说法，错误的是（ ）。2015年",[578,580,582,584],{"key":20,"text":579,"correct":22},"一般情况下，项目施工初期的曲线斜率是逐渐增大的",{"key":24,"text":581,"correct":29},"一般情况下，项目施工后期的曲线为凹型",{"key":27,"text":583,"correct":22},"通过对“S”曲线的形状分析，可以定性分析施工组织设计中工作内容安排的合理",{"key":31,"text":585,"correct":22},"在项目实施过程中，“S”曲线可结合工程进度管理曲线（“香蕉”曲线）进行施工进度、费用控制",{"id":587,"libraryId":5,"type":15,"typeLabel":16,"stem":588,"options":589,"answer":24,"analysis":33},1134614,"公路工程进度计划的主要形式中，既能反映各分部（项）工程的进度，又能反映工程总体进度的是（ ）。2017真题",[590,592,594,596],{"key":20,"text":591,"correct":22},"时标网络图",{"key":24,"text":593,"correct":29},"“S”曲线和横道图结合的公路工程进度表",{"key":27,"text":595,"correct":22},"单代号搭接网络图",{"key":31,"text":597,"correct":22},"“S”曲线",[599,602,605,608,611,614],{"id":15,"name":600,"category":7,"favorite":601},"领导干部任职前廉政法规知识测试题",92,{"id":603,"name":604,"category":7,"favorite":15},595,"建筑结构与设备",{"id":606,"name":607,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":609,"name":610,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":612,"name":613,"category":7,"favorite":8},534,"BIM工程师",{"id":615,"name":613,"category":7,"favorite":8},535]