[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135289":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135289,796,2,"多选题","桥梁施工模板、支架设计计算中，应考虑的荷载包括（ ）。2012年",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","汽车荷载",false,{"key":16,"text":17,"correct":18},"B","模板、支架及施工人员、材料、机具的重量",true,{"key":20,"text":21,"correct":18},"C","新浇筑混凝土对侧模板的压力",{"key":23,"text":24,"correct":18},"D","倾倒混凝土时产生的水平荷载",{"key":26,"text":27,"correct":18},"E","可能产生的雪荷载、冬季保温设施荷载","BCDE","计算模板、支架和拱架时，应考虑下列荷载：（1）模板、支架和拱架自重；（2）新浇筑混凝土、钢筋混凝土或其他圬工结构物的重力；（3）施工人员和施工材料、机具等行走运输或堆放的荷载；（4）振捣混凝土时产生的荷载；（5）新浇筑混凝土对侧面模板的压力；（6）混凝土入模时产生的水平方向的冲击载荷；（7）设置与水中的支架所承受的水流压力、波浪力、流冰压力、船只及其他漂浮物的撞击力；（8）其他可能产生的荷载，如雪荷载、冬季保温设施荷载等。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]