[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135275":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135275,796,2,"多选题","关于乳化沥青碎石基层施工的说法，正确的有（ ）。2012年",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","乳化沥青碎石混合料必须采用拌和机拌和",false,{"key":16,"text":17,"correct":18},"B","混合料的拌和、运输、摊铺应在乳液破乳之前结束",true,{"key":20,"text":21,"correct":14},"C","乳化沥青破乳之前，应完成所有碾压工作",{"key":23,"text":24,"correct":18},"D","拌和过程中已发生破乳的混合料，应予废弃",{"key":26,"text":27,"correct":18},"E","施工过程中遇雨应停止铺筑，以防止雨水将乳液冲走","BDE","路面沥青稳定基层（底基层）施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]