[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135267":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135267,796,2,"多选题","关于路基冬期施工说法，正确的有（）2016年",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","冬期填筑的路堤，每层每侧应超填并压实",true,{"key":16,"text":17,"correct":14},"B","挖填方交界处，填土低于 1m的路堤都不应在冬期填筑",{"key":19,"text":20,"correct":21},"C","当路基填至路床底面时，应碾压密实后停止填筑",false,{"key":23,"text":24,"correct":14},"D","当天填的土必须当天完成碾压",{"key":26,"text":27,"correct":14},"E","挖方边坡不应一次挖到设计线","ABDE","当路堤高距路床底面 1m时，应碾压密实后停止填筑。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]