[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135253":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135253,796,2,"多选题","关于施工标准化与安全措施费的说法，正确的有（ ）。2014年",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","指工程施工期间为满足安全生产、施工标准化、规模化、精细化所发生的费用",true,{"key":16,"text":17,"correct":18},"B","该费用包括施工期间为保证交通安全而设置的临时安全设施的标志、标牌的费用",false,{"key":20,"text":21,"correct":14},"C","该费用不包括预制场、拌合站、临时便道、临时便桥的施工标准化费用",{"key":23,"text":24,"correct":18},"D","该费用以各类工程的直接费之和为计算基数",{"key":26,"text":27,"correct":18},"E","作为规费的组成部分，其费率由交通主管部门统一发布","AC","施工标准化与安全措施费：指工程施工期问为满足安全生产、施工标准化、规范化、精细化所发生的费用。该费用不包括施工期间为保证交通安全而设置的临时安全设施和标志、标牌的费用，需要时，应根据设计要求计算。该费用也不包括预制场、拌和站、临时便道、临时便桥的施工标准化费用，应根据施工组织标准化要求单独计算。施工标准化与安全措施费以各类工程的直接工程费之和为计算基数。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]