[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135252":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135252,796,2,"多选题","根据《公路工程标准施工招标文件》（2009 年版）合同文件范本，关于计量支付管理的说法，错误的有（ ）。2013年",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人应对已完成的分项工程向业主申请质量认证",true,{"key":16,"text":17,"correct":18},"B","承包人应在协议约定的时间内向监理工程师申请计量",false,{"key":20,"text":21,"correct":18},"C","监理工程师应对实际完成的工程量进行计量，并签发计量证书给承包人",{"key":23,"text":24,"correct":14},"D","承包人可凭质量认证和计量证书向业主提出付款申请",{"key":26,"text":27,"correct":14},"E","应向监理工程师复核申报资料，确定支付款项，并批准向承包人付款","ADE","对已完成的分项工程向监理工程师申请质量认证。错。承包人凭质量认证和计量证书向监理工程师提出付款申请。错。监理工程师复核申报资料，确定支付款项，向业主提供付款证明文件。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]