[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135249":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135249,796,2,"多选题","（2019年真题）材料预算价包括（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","材料原价",true,{"key":16,"text":17,"correct":14},"B","运杂费",{"key":19,"text":20,"correct":21},"C","场内、外运输损耗",false,{"key":23,"text":24,"correct":14},"D","采购及保管费",{"key":26,"text":27,"correct":21},"E","操作性磨损","ABD","P378-382 本题考查的是公路项目标后预算编制。材料预算价格由材料原价、运杂费、场外运输损耗、采购及仓库保管费组成，其中材料原价、运杂费按不含增值税（可抵扣进项税额）的价格确定。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]