[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135242":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135242,796,2,"多选题","下列内容中，属于施工总体部署主要内容的有（）。2018真题",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建立施工管理机构",true,{"key":16,"text":17,"correct":14},"B","划分施工任务",{"key":19,"text":20,"correct":21},"C","编制施工进度计划",false,{"key":23,"text":24,"correct":14},"D","确定施工顺序",{"key":26,"text":27,"correct":21},"E","制定各项资源需求计划","ABD","本题考查的是公路工程施工组织的特点与主要内容。施工总体部署主要内容包括：建立施工管理机构、施工任务划分、施工顺序。参见教材。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]