[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135239":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135239,796,2,"多选题","根据工程技术档案管理的要求，工程完工验收后，施工单位应交建设单位保管的资料有（ ）。2013年",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","竣工图表",true,{"key":16,"text":17,"correct":14},"B","隐蔽工程验收记录",{"key":19,"text":20,"correct":14},"C","永久性水准点的位置",{"key":22,"text":23,"correct":24},"D","施工经验总结",false,{"key":26,"text":27,"correct":24},"E","施工日记","ABC","第一部分是工程完工验收后，交建设单位保管的。其内容有：1．竣工图表；2．图纸会审记录、设计变更和技术核定单；3．材料、构件的质量合格证明；4．隐蔽工程验收记录；5．工程质量检查评定和质量事故处理记录；6．主体结构和重要部位的试件、试块、材料试验、检查记录；7．永久性水准点的位置，构造物在施工过程中测量定位记录，有关试验观测记录； 8．其他有关该项工程的技术决定。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]