[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135224":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135224,796,2,"多选题","承包人未在施工现场设立项目管理机构和派驻相应人员对分包工程的施工活动实施有效管理，并且有下列情形中，属于转包的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人将工程分包给不具备相应资格的企业或者个人的",false,{"key":16,"text":17,"correct":14},"B","分包合同未报发包人备案的",{"key":19,"text":20,"correct":21},"C","承包人将承包的全部工程发包给他人的",true,{"key":23,"text":24,"correct":14},"D","分包人将分包工程再进行分包的",{"key":26,"text":27,"correct":21},"E","承包人将承包的全部工程肢解后以分包的名义分别发包给他人的","CE","2020版教材P445\u002F2019版教材P436 承包人未在施工现场设立项目管理机构和派驻相应人员对分包工程的施工活动实施有效管理，并且有下列情形之一的，属于转包：（1）承包人将承包的全部工程发包给他人的；（2）承包人将承包的全部工程肢解后以分包的名义分别发包给他人的；（3）法律、法规规定的其他转包行为。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]