[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135204,796,2,"多选题","悬臂梁浇筑施工中应注意要点（ ）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","主梁各部分的长度应充分考虑主梁的形式，跨径，墩宽等来确定",true,{"key":16,"text":17,"correct":14},"B","桥墩顶梁段及桥墩附近梁段施工时，可采用托架或膺架为支架就地浇筑混凝土",{"key":19,"text":20,"correct":14},"C","在梁段混凝土浇筑前，应对挂篮，模板，预应力筋管道，钢筋等接缝处理情况进行全面检查，经确认后方可浇筑",{"key":22,"text":23,"correct":14},"D","若梁身与墩身采用非刚性连接，为保证结构的稳定性，悬臂梁和连续梁桥应实施0号梁段与桥墩间临时固结支承措施",{"key":25,"text":26,"correct":27},"E","挂篮安装无须保证安全，稳定、可靠",false,"ABCD","2020版教材P185\u002F2019版教材P178 1.主梁各部分的长度应充分考虑主梁的形式、跨径、墩宽、挂篮的形式以及施工周期来确定。0号段长度一般为5~20m，悬浇分段长度一般为3~5m。2.桥墩顶梁段及桥墩顶附近梁段施工时，可采用托架或膺架为支架就地浇筑混凝土。托架或膺架应经过设计，计算弹性及非弹性变形。3.在梁段混凝土浇筑前，应对挂篮（托架或膺架）、模板、预应力筋管道、钢筋、预埋件、混凝土材料、配合比、机械设备、混凝土接缝处理情况进行全面检查，经确认后方可浇筑。4.悬臂施工过程中，若梁身与墩身采用非刚性连接，为保证结构的稳定性，悬臂梁桥和连续梁桥应实施0号块梁段与桥墩间临时固结支承措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]