[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135185":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135185,796,2,"多选题","钻孔灌注桩施工步骤包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","钢筋笼制作",true,{"key":16,"text":17,"correct":14},"B","埋设护筒",{"key":19,"text":20,"correct":14},"C","钻孔",{"key":22,"text":23,"correct":24},"D","孔内通风",false,{"key":26,"text":27,"correct":14},"E","制备泥浆","ABCE","2020版教材P156\u002F2019版教材P147 钻孔灌注桩施工的主要工序有：埋设护筒、制备泥浆、钻孔、清底、钢筋笼制作与吊装以及灌注水下混凝土等。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]