[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135177":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135177,796,2,"多选题","下列预应力张拉要求中，错误的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有几套张拉设备时，可根据现场情况随机组合使用",true,{"key":16,"text":17,"correct":18},"B","进行张拉作业前，必须对千斤顶进行标定",false,{"key":20,"text":21,"correct":18},"C","当梁体混凝土强度达到设计规定的张拉强度时，方可进行张拉",{"key":23,"text":24,"correct":14},"D","预应力张拉以实际伸长量控制为主",{"key":26,"text":27,"correct":18},"E","预应力钢筋张拉时，应先调整到初应力再开始张拉和量测伸长值","AD","2020版教材P145\u002F2019版教材P141 2.张拉用的千斤顶与压力表应配套标定、配套使用，标定应在经国家授权的法定计量技术机构定期进行，标定时千斤顶活塞的运行方向应与实际张拉工作状态一致。当处于下列情况之一时，应重新进行标定。 2.预应力筋采用应力控制方法张拉时，应以伸长值进行校核，实际伸长值与理论伸长值的差值应符合设计要求，设计无规定时，实际伸长值与理论伸长值的差值应控制在6%以内，否则应暂停张拉，待查明原因并采取措施予以调整后，方可继续张拉。。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]