[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135175":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135175,796,2,"多选题","模板、拱架和支架施工方案的内容应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工艺图",true,{"key":16,"text":17,"correct":18},"B","支架预算书",false,{"key":20,"text":21,"correct":14},"C","强度计算书",{"key":23,"text":24,"correct":14},"D","稳定性计算书",{"key":26,"text":27,"correct":14},"E","刚度计算书","ACDE","2020版教材P126\u002F2019版教材P122 承包人应在制作模板、拱架和支架前14d，向监理工程师提交模板、拱架和支架的施工方案，施工方案应包括工艺图和强度、刚度与稳定性等的计算书，经监理工程师批准后才能制作和架设。监理工程师的批准及制作、架设过程中的检查，并不免除承包人对此应负的责任。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]