[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135168":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135168,796,2,"多选题","关于模板、支架和拱架拆除的说法中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢筋混凝土结构的承重模板、支架和拱架，应在混凝土强度能承受其自重荷载及其他可能的叠加荷载时，方可拆除",true,{"key":16,"text":17,"correct":18},"B","现浇混凝土拱圈的拱架，拆除期限应符合设计规定；设计未规定时，应在拱圈混凝土强度达到设计强度的75%后，方可拆落拆除",false,{"key":20,"text":21,"correct":18},"C","跨径小于10m的小拱桥，宜在护拱砌完后卸架",{"key":23,"text":24,"correct":18},"D","模板拆除应遵循先支先拆，后支后拆的顺序",{"key":26,"text":27,"correct":14},"E","承包人应在拟定拆模时间的12h以前，向监理工程师报告拆模建议，并应取得监理工程师同意","AE","2020版教材P133\u002F2019版教材P128 现浇混凝土拱圈的拱架.拆除期限应符合设计规定；设计未规定时，应在拱圈混凝土强度达到设计强度的85%后，方可拆落拆除，故B选项错误。跨径小于10m的小拱桥，宜在拱上建筑全部完成后卸架；中等跨径的实腹式拱，宜在护拱砌完后卸架，故c选项错误。模板拆除应按设计的顺序进行，设计无规定时，应遵循先支后拆，后支先拆的顺序，故D选项错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]