[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135115":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135115,796,2,"多选题","热拌沥青混凝土路面施工时，在监理工程师批准的现场备齐全部机械设备进行试验段铺筑，以确定（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","松铺系数",true,{"key":16,"text":17,"correct":14},"B","压实遍数",{"key":19,"text":20,"correct":14},"C","施工工艺",{"key":22,"text":23,"correct":14},"D","机械配备",{"key":25,"text":26,"correct":27},"E","地基回弹模量",false,"ABCD","2020版教材P85\u002F2019版教材P80 试验段开工前28d安装好试验仪器和设备，配备好的试验人员报请监理工程师审核。各层开工前14d在监理工程师批准的现场备齐全部机械设备进行试验段铺筑，以确定松铺系数、施工工艺、机械配备、人员组织、压实遍数，并检查压实度，沥青含量，矿料级配、沥青混合料马歇尔各项技术指标等。而选项E主要是用于道路设计的指标，",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]