[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135104":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135104,796,2,"多选题","关于无机结合料稳定材料层之间处理的说法中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","在上层结构施工前，应将下层养护用材料彻底清理干净",true,{"key":16,"text":17,"correct":14},"B","应采用人工、小型清扫车以及洒水冲刷的方式将下层表面的浮浆清理干净",{"key":19,"text":20,"correct":21},"C","下承层局部存在松散现象时，无需彻底清理干净",false,{"key":23,"text":24,"correct":14},"D","在上层施工前1～2h，宜撒布水泥或洒铺水泥净浆",{"key":26,"text":27,"correct":21},"E","禁止采用上下结构层连续摊铺施工的方式","ABD","2020版教材P76\u002F2019版教材P71 应采用人工、小型清扫车以及洒水冲刷的方式将下层表面的浮浆清理干净。下承层局部存在松散现象时，也应彻底清理干净。可采用上下结构层连续摊铺施工的方式，每层施工应配备独立的摊铺和碾压设备，不得采用一套设备在上下结构层来回施工。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]