[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135083":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135083,796,2,"多选题","下列关于对急流槽的施工要求描述正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","急流槽必须用浆砌圬工结构",true,{"key":16,"text":17,"correct":14},"B","急流槽的纵坡不宜超过1：1.5，同时应与天然地面坡度相配合",{"key":19,"text":20,"correct":14},"C","当急流槽很长时，应分段砌筑，每段不宜超过10m",{"key":22,"text":23,"correct":24},"D","当急流槽较长时，槽底可用几个纵坡，一般是上段较缓，向下逐渐放陡",false,{"key":26,"text":27,"correct":24},"E","急流槽的平面转弯半径应大于20m","ABC","2020版教材P44\u002F2019版教材P38 该题主要考察的是：跌水与急流槽跌水与急流槽的施工应符合下列规定：1．跌水与急流槽必须用浆砌圬工结构，跌水的台阶高度可根据地形、地质等条件决定，多级台阶的各级高度可以不同，其高度与长度之比应与原地面坡度相适应。2．急流槽的纵坡不宜超过1:1.5，同时应与天然地面坡度相配合。当急流槽较长时，槽底可用几个纵坡，一般是上段较陡，向下逐渐放缓。3．当急流槽很长时，应分段砌筑，每段不宜超过l0m，接头用防水材料填塞，密实无空隙。4、急流槽的砌筑应使自然水流与涵洞进、出口之间形成一个过渡段，基础应嵌入地面以下，基底要求砌筑抗滑平台并设置端护墙。5、路堤边坡急流槽的修筑，应能为水流入排水沟提供一个顺畅通道，路缘石开口及流水进入路堤边坡急流槽的过渡段应连接圆顺。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]