[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135072":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135072,796,2,"多选题","关于冬期开挖路堑的说法中，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","当冻土层被开挖到未冻土后，应连续作业，分层开挖",true,{"key":16,"text":17,"correct":14},"B","挖方边坡不应一次挖到设计线，应预留一定厚度的覆盖层，待到正常施工季节再削去预留台阶，整理达到设计边坡",{"key":19,"text":20,"correct":14},"C","路堑挖至路床面以上1m时，挖好临时排水沟后，应停止开挖并在表面覆以雪或松土",{"key":22,"text":23,"correct":24},"D","冬期开挖路堑可以从下向上掏空挖“神仙土”",false,{"key":26,"text":27,"correct":24},"E","弃土堆高度最高可为5m，弃土堆坡脚到路堑边坡顶的距离一般不得小于3m","ABC","2020版教材P15 （1）挖方边坡不应一次挖到设计线，应预留一定厚度的覆盖层，待到正常施工季节再削去预留台阶，整理达到设计边坡。（2）路堑挖至路床面以上1m时，挖好临时排水沟后，应停止开挖并在表面覆以雪或松土，待到正常施工时，再挖去其余部分。 【2020变动】 @##",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]