[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135058":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135058,796,2,"多选题","关于滑坡地段路基的施工技术要点的说法中，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","滑坡整治宜在旱季施工",true,{"key":16,"text":17,"correct":14},"B","施工时应采取措施截断流向滑坡体的地表水、地下水及临时用水",{"key":19,"text":20,"correct":14},"C","滑坡体未处理之前，严禁在滑坡体上增加荷载，严禁在滑坡前缘减载",{"key":22,"text":23,"correct":24},"D","采用削坡减载方案整治滑坡时，减载应自下而上进行，严禁超挖或乱挖，严禁爆破减载",false,{"key":26,"text":27,"correct":24},"E","采用加填压脚方案整治滑坡时，可以因为加填压脚土而堵塞原有地下水出口","ABC","2020版教材P34\u002F2019版教材P31 滑坡地段路基的施工技术要点1.滑坡地段施工前，应制定应对滑坡或边坡危害的安全预案，施工过程中应进行监测。2.滑坡整治宜在旱季施工。需要在冬期施工时，应了解当地气候、水文情况，严格按照冬期施工的有关规定实施。3.路基施工应注意对滑坡区内其他工程和设施的保护。在滑坡区内有河流时，应尽量避免因滑坡工程的施工使河流改道或压缩河道。4.滑坡整治，应及时采取技术措施封闭滑坡体上的裂隙，应在滑坡边缘一定距离外的稳定地层上，按设计要求并结合实际情况修筑一条或数条环形截水沟，截水沟应有防渗措施。5.施工时应采取措施截断流向滑坡体的地表水、地下水及临时用水。6.滑坡体未处理之前，严禁在滑坡体上增加荷载，严禁在滑坡前缘减载。7.滑坡整治完成后，应及时恢复植被。8.采用削坡减载方案整治滑坡时，减载应自上而下进行，严禁超挖或乱挖，严禁爆破减载。采用加填压脚方案整治滑坡时，只能在抗滑段加重反压，并且做好地下排水，不得因为加填压脚土而堵塞原有地下水出口。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]