[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135046":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135046,796,2,"多选题","柴油发电机组的安装要求有()",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发电机的无需做静态和运转试验",false,{"key":16,"text":17,"correct":18},"B","柴油发电机馈电线路连接后，两端的相序必须与原供电系统相序一致",true,{"key":20,"text":21,"correct":18},"C","发电机中性线（工作零线）应与接地干线直接连接",{"key":23,"text":24,"correct":18},"D","发电机组至低压配电柜馈电线路的相间、相对地间的绝缘电阻值应大于0.5MΩ",{"key":26,"text":27,"correct":14},"E","塑料绝缘电缆线路直流耐压试验为2.4kV，时间为5min，泄漏电流稳定，无击穿现象","BCD","2020版教材P286\u002F2019版教材P280 柴油发电机组安装要求1.柴油发电机馈电线路连接后，两端的相序必须与原供电系统相序一致。2.发电机中性线（工作零线）应与接地干线直接连接。3.发电机组至低压配电柜馈电线路的相间、相对地间的绝缘电阻值应大于0.5MQ;塑料绝缘电缆线路直流耐压试验为2.4kV，时间为15min，泄漏电流稳定，无击穿现象。4.发电机的试验必须符合《建筑电气工程施工质量验收规范》GB 50303—2002附录A中规定的发电机的静态和运转试验标准。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]