[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1135028":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1135028,796,2,"多选题","隧道超欠挖原因有()",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","测量放样错误或误差较大",true,{"key":16,"text":17,"correct":14},"B","钻孔操作台架就位不准确",{"key":19,"text":20,"correct":21},"C","爆破员操作不熟练",false,{"key":23,"text":24,"correct":14},"D","装药量及装药结构不合理",{"key":26,"text":27,"correct":14},"E","爆破网路联接不规范","ABDE","2020版教材P266\u002F2019版教材P260 —、原因分析(一）测量放样错误或误差较大(二）钻孔操作台架就位不准确(三）司钻工操作不熟练。(四）装药量及装药结构不合理。(五）爆破网路连接不规范。(六）其他原因：围岩节理发育，层面倾角小，爆后拱顶呈方形塌落，而未能形成弧形，也会产生超挖。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]