[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134999":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134999,796,2,"多选题","场地建设前施工单位应将梁场布置方案报监理工程师审批，方案内容应包含各类型梁板的（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","台座数量",true,{"key":16,"text":17,"correct":14},"B","模板数量",{"key":19,"text":20,"correct":14},"C","生产能力",{"key":22,"text":23,"correct":14},"D","最大存梁能力",{"key":25,"text":26,"correct":27},"E","生产成本",false,"ABCD","2020版教材P413\u002F2019版教材P405 场地建设前施工单位应将梁场布置方案报监理工程师审批，方案内容应包含各类型梁板的台座数量、模板数量、生产能力、存梁区布置及最大存梁能力等。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]