[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134988":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134988,796,2,"多选题","工程价款价差调整的主要方法有（ ）法几种。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","调值公式",true,{"key":16,"text":17,"correct":14},"B","调价文件计算",{"key":19,"text":20,"correct":21},"C","预算价格调整",false,{"key":23,"text":24,"correct":14},"D","实际价格调整",{"key":26,"text":27,"correct":14},"E","工程造价指数调整","ABDE","2020版教材P399\u002F2019版教材P391 工程价款价差调整的主要方法：1.工程造价指数调整法。2.实际价格调整法。3.调价文件计算法。4.调值公式法。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]