[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134985":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134985,796,2,"多选题","成本目标通常以（ ）来定量地表示。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","控制项目总成本额",false,{"key":16,"text":17,"correct":14},"B","控制项目的人工消耗率",{"key":19,"text":20,"correct":21},"C","项目成本总降低额",true,{"key":23,"text":24,"correct":14},"D","控制项目的材料节约率",{"key":26,"text":27,"correct":21},"E","项目成本总降低率","CE","2020版教材P378\u002F2019版教材P370 成本目标通常以项目成本总降低额和降低率来定量地表示。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]