[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134977":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134977,796,2,"多选题","工期延误按索赔结果分为（ ）延误。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","可原谅可补偿",true,{"key":16,"text":17,"correct":14},"B","可原谅不可补偿",{"key":19,"text":20,"correct":14},"C","不可原谅",{"key":22,"text":23,"correct":24},"D","关键性",false,{"key":26,"text":27,"correct":24},"E","非关键性","ABC","2020版教材P372\u002F2019版教材P365 工期延误按索赔结果分为可原谅可补偿的延误，可原谅不可补偿的延误，不可原谅的延误。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]