[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134965":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134965,796,2,"多选题","先简支后连续梁桥的施工质量控制要点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预制拼装",false,{"key":16,"text":17,"correct":18},"B","后浇段工艺控制",true,{"key":20,"text":21,"correct":18},"C","体系转换工艺控制",{"key":23,"text":24,"correct":18},"D","后浇段收缩控制",{"key":26,"text":27,"correct":18},"E","临时支座安装与拆除控制","BCDE","2020版教材P324\u002F2019版教材P318 先简支后连续：后浇段工艺控制、体系转换工艺控制、后浇段收缩控制、临时支座安装与拆除控制。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]